TCN Boosts Power Capacity in Port Harcourt

14

Chioma Eche, Abuja

The Transmission Company of Nigeria (TCN) has commissioned a 100MVA, 132/33kV power transformer at its Port Harcourt Main Substation, enhancing the bulk transmission capability of the substation by 80 MW.

This initiative, which is a TCN-World Bank project, also includes the complete rehabilitation and expansion of the 132/33 kV transmission substation and the addition of three feeders and associated accessories.

With the installation of the 100MVA power transformer, the substation’s installed capacity increased from 180MVA to 280MVA.

Also, notably, industries in the Trans Amadi industrial environment and communities beyond Port Harcourt city are expected to benefit significantly from this capacity expansion.

According to the Commission’s report, the first quarter of this year has executed several projects in its Port-Harcourt Region and currently has several ongoing projects that are at various completion stages, including a 100MVA transformer installation in Port Harcourt Town, which will soon be completed and commissioned.

It says transformer projects are equally ongoing in Port-Harcourt Town, Itu, Umuahia, Aba, and Alaoji, aimed at bolstering bulk power transmission within the region.

In its Port Harcourt Sub-region, TCN recently received four power transformers, including two units of 100MVA capacity transformers, one each at Port Harcourt Main and Port Harcourt Town transmission substations, and two units of 60MVA power transformers, one each sent to Rumuosi and Port Harcourt Main transmission substations.

Also Read: Gas Shortage: TCN Seeks Improved Power Generation Strategies

“Collectively, these will increase available capacity within TCN’s Port Harcourt region for Port Harcourt Distribution Company to offtake for its customers.”

At the Uyo Work Centre, TCN is also currently upgrading the Itu Substation with a 60MVA 132kV transformer and associated switch gears. Upon completion, the station’s capacity will increase by 48MW.

TCN further disclosed that ongoing new substation projects within the region include the construction of a 2x60MVA 132/33kV transmission substation at Oron and a 2×30/40MVA 132/33kV Substation at Ididep both in Calabar.

The Transmission Company of Nigeria, TCN, said this increased maintenance efficiency and invariably reduced downtime in the Regional Store, which received bulk consignments of spare parts, including circuit breakers, 33kV lighting arresters, battery chargers, battery banks, toolboxes, and safety kits.

TCN remains steadfast in its effort to put in place a robust and more efficient transmission grid through strategic initiatives and project implementation across regions.

It also added that the Commission is committed to swift maintenance and fault response by ensuring it has available and necessary spare parts in its stores nationwide.