Government inaugurates major power substation in Anambra

By Golfa Francis, Abuja

0 535
The Nigerian government has commissioned the 2x60MVA, 132/33KV Awka Substation in Anambra State, built by the Niger Delta Power Holding Company Limited (NDPHC) to improve power supply to the state.
 
Vice President, Professor Yemi Osinbajo while commissioning the substation reiterated government’s commitment towards creating enabling environment for businesses to grow in Nigeria.
He noted that for Nigeria’s economy to grow at required rate, small businesses have to be supported by both the Federal and State governments.
The Vice President disclosed that the new substation, built by the NDPHC, will deliver about 100 Mega Watts of power to the Anambra state capital and its environs.
The economy of Nigeria largely depends on effort that is made at the sub-national level, that’s the state level. It is the aggregation of the work that is done in the states that leads to the great economy that we hope for and are working for in this nation of ours,” he said.
“Anambra State revenue has increased from about N10.4 billion in 2014 to N26.37 billion as 2019 and this is another 152 percent increase in the state’s IGR,” Professor Osibanjo stated.
He said that the enabling environment and ease of doing business measures that have been implemented in Anambra state has seen the state becoming one of the fastest growing manufacturing hubs in the country.
He is of the opinion that Nnewi, which houses key local manufacturing companies including Innoson Vehicles Manufacturing, Tommy Tommy Industries, Chikason Group amongst others is evidence of the entrepreneurial ability of the Nigerian people and their drive due to the enabling environment created by the state.
Vice President Osinbajo who is also the Chairman of NDPHC Board, emphasised that the way the economy will develop is through small businesses powered by states and assisted by as much as possible, the Federal Government.
While pointing out that the industrial growth of the state happened despite power supply challenge, the Vice President noted that the new substation was a direct measure by the government to address the challenge.
According to him, “Since the technical commissioning of the substation in November 2020, this new substation has been in service providing 33KV evacuation capacity for at least 100MW of power through its two units of 60MVA, a total of 120MVA.”
Also speaking, the Anambra state Governor, Chief Willie Obiano thanked the Federal Government and the NDPHC for constructing the substation, saying it will greatly boost the industrialisation of the state.
Governor Obiano noted that with improved power supply to the state, many industries would save the cost of self generation of electricity.
He stated that the newly commissioned shoe making factory and the cargo airport would be direct beneficiaries of the new substation.
The Managing Director of NDPHC, Mr. Chiedu Ugbo disclosed that besides the industries, about a million households in Awka and its environs will benefit from improved power supply.
He explained that the project is one of the several transmission projects conceived under the National Integrated Power Project (NIPP) being implemented by NDPHC as part of the effort of the government to improving electricity transmission infrastructure in the country.
The Substation is provided with six 33kV feeders to enable robust power evacuation to the following hitherto constrained locations of the EEDC Franchise territory of Anambra State, including two premium new locations critical to the Anambra State Government,” Mr Ugbo said.
NDPHC has recently completed a 32Km of line with one unit of 2.5MVA and injection substation to the new airport in the state.
The feeder from the Awka transmission substation will be supplying close to one million households spread over the urban and rural parts of this state including existing and upcoming industrial layouts, factories, markets and other critical state infrastructures,” he stated.
The Managing Director of News Engineering, the EPC contractor, Josephine Nwaeze disclosed the project executed solely by Nigerians.
She called on the Federal Government to make more projects available to indigenous companies to grow the economy.
Lateefah Ibrahim
Leave A Reply

Your email address will not be published.