The Federal Government has commissioned new power transformers at transmission substations in Gombe metropolis and Billiri, in a major upgrade expected to improve electricity supply, strengthen network reliability and support economic activities across Gombe State and neighbouring communities.

The projects, funded by the World Bank, have increased the transmission capacity of the two facilities, providing additional capacity to meet growing electricity demand and address persistent supply constraints in the areas.

At the newly constructed Billiri 132/33kV transmission substation, two 60MVA power transformers have been installed, providing a combined transformation capacity of 120MVA, equivalent to 96MW.

The facility, located in Billiri Local Government Area, is also equipped with six 33kV outgoing distribution feeders and is expected to strengthen bulk electricity supply to Billiri, Numan in Adamawa State and adjoining communities.

READ ALSO: Gombe Governor Launches 7.5MVA Power Project for Industrial Park

The development is expected to improve electricity availability to households, businesses, industries and public institutions, while creating opportunities for increased commercial and agricultural activities.

In Gombe metropolis, the existing transmission substation has also received a significant capacity upgrade with the installation of a new 300MVA, 330/132kV transformer and the replacement of an existing 30MVA, 132/33kV transformer with a 100MVA unit.

The intervention has increased the substation’s transformation capacity at the 330/132kV level from 300MVA to 600MVA, equivalent to 480MW, while capacity at the 132/33kV level has risen from 150MVA to 220MVA, equivalent to 176MW.

The Minister of Power, Mr. Joseph Olasunkanmi Tegbe, said the projects reflected President Bola Tinubu’s commitment to repositioning the power sector as a driver of industrialisation, economic growth and national prosperity.

He said the investments would strengthen the economic foundation of communities whose productive potential had been limited by inadequate electricity infrastructure.

According to him, Billiri occupies an important position in the economic and social development of Gombe State, with its commercial activities, agriculture, small businesses and emerging enterprises requiring reliable electricity to thrive.

Mr. Tegbe said the project demonstrated the Federal Government’s determination to ensure that communities were not denied opportunities for economic advancement because of inadequate infrastructure.

He added that the improved transmission facilities would provide a stronger electricity backbone for Billiri and neighbouring communities, enabling businesses to expand and supporting increased economic activities.

Speaking at the commissioning ceremony, the Managing Director and Chief Executive Officer of the Transmission Company of Nigeria (TCN), Mr. Sule Ahmed Abdulaziz, said Gombe State and other parts of the North-East would benefit from increased electricity transmission capacity following the installation of the new transformers.

Mr. Abdulaziz explained that the previous capacity of the Gombe Transmission Substation had become inadequate to meet the growing electricity demand in the state and other areas served by the facility.

He described the upgrade as a significant development for Gombe State and the wider North-East, saying it would give system operators greater flexibility in managing electricity transmission and improve the reliability of the regional network.

In his keynote address, Governor Muhammadu Inuwa Yahaya, represented by the Commissioner for Energy and Mineral Resources, Mr. Sanusi Pindiga, commended President Tinubu for signing the Electricity Act 2023 and sustaining infrastructure development in the power sector.

He described the commissioning as another milestone in efforts to strengthen electricity infrastructure, improve transmission capacity and accelerate socio-economic development in Gombe State and the North-East.

Mr. Pindiga said the occasion was not merely about commissioning power transformers but also about investing in the future of the people, expanding businesses, growing the economy and creating an enabling environment for sustainable community development.

He noted that the new installations, alongside associated high-voltage switchgear, protection systems and additional feeder facilities, would help address critical transmission constraints and improve the capacity and operational flexibility of the electricity network.

The commissioner said the state government was particularly interested in ensuring that improved electricity infrastructure supported its industrial and commercial development priorities, including agro-processing facilities, small and medium-sized enterprises, industrial clusters and other productive ventures.

He urged residents, businesses and public institutions to embrace energy efficiency and responsible electricity consumption to maximise the benefits of the investments.

Also, the traditional Ruler in Billiri, Mai Tangle, His Royal Highness, Danladi Sanusi Maiyamba, appreciate the Federal Government on behalf of the people of Tangale Chiefdom, saying the power project is more than an electricity infrastructure, but a representation of hope, progress, economic empowerment and a brighter future for his people.

RELATED ARTICLES

LEAVE A REPLY